Build STL: Killark Properties Acquisition and Maintenance 21-SLFRF-40

Funding to expand the pipeline of contractors and developers operating in QCTs by: i) establishing a Contractor/Developer training program and facility; ii) subsidizing contractor insurance and bonding costs; iii) providing contractors/developers patient capital to support capacity building; iv) subsidizing construction apprenticeships.

Project Appropriation

Project Appropriation
$4,250,000.00

Total Programmed Funds

Total Programmed Funds
$4,250,000.00
100.0% programmed of total appropriation

Total Expenditures

Total Expenditures
$2,705,941.72
63.7% expended of total appropriation

Project Expenditures

Project Expenditures
Date Account Vendor Amount
11/15/2023 566050 LAND CLEARANCE FOR REDEVELOPMENT AUTHORITY $2,705,941.72

Definitions

  • Appropriated Funds: Total amount of authorized funding set aside for a specific purpose
  • Programmed Funds: Estimate and Apportionment (E&A) approved contracts, personnel services, Board Bill approved Intergovernmental agreements (IGA)
  • Expenditures: Total amount spent by departments

Notes and Contact

ARPA(SLFRF and ERA) reporting will be updated on a rolling monthly basis.

The Project and Expenditure data reported is through April 30, 2024.

The data was last updated on May 10, 2024.

ARPA - American Rescue Plan Act ($510,518,052.20)
SLFRF - Coronavirus State and Local Fiscal Recovery Funds ($498,076,054.00)
ERA - Emergency Rental Assistance ($12,441,998.20)

Please contact STLARPA@stlouis-mo.gov if you have questions about the data.