Micro Transit 71591

On-demand microtransit service in Downtown and near north St. Louis neighborhoods. Small electric vehicles hailed by phone, app, or on-street. Service area was expanded in February 2023 after a pilot throughout 2022. The focus of this project is resident and visitor transportation within a relatively small defined area, and ast mile connections to the MetroLink system.

Project Appropriation

Project Appropriation
$999,396.00

Total Programmed Funds

Total Programmed Funds
$999,396.00
100.0% programmed of total appropriation

Total Expenditures

Total Expenditures
$782,136.00
78.3% expended of total appropriation

Project Expenditures

Project Expenditures
Date Account Vendor Amount
03/02/2023 566000 LABYRINTH SMART MOBILITY INC $43,452.00
04/07/2023 566000 LABYRINTH SMART MOBILITY INC $43,452.00
05/01/2023 566000 LABYRINTH SMART MOBILITY INC $43,452.00
06/01/2023 566000 LABYRINTH SMART MOBILITY INC $43,452.00
07/05/2023 566000 LABYRINTH SMART MOBILITY INC $43,452.00
08/01/2023 566000 LABYRINTH SMART MOBILITY INC $43,452.00
08/31/2023 566000 LABYRINTH SMART MOBILITY INC $43,452.00
10/03/2023 566000 LABYRINTH SMART MOBILITY INC $43,452.00
11/01/2023 566000 LABYRINTH SMART MOBILITY INC $43,452.00
12/01/2023 566000 LABYRINTH SMART MOBILITY INC $43,452.00
01/02/2024 566000 LABYRINTH SMART MOBILITY INC $43,452.00
02/01/2024 566000 LABYRINTH SMART MOBILITY INC $43,452.00
03/01/2024 566000 LABYRINTH SMART MOBILITY INC $43,452.00
04/01/2024 566000 LABYRINTH SMART MOBILITY INC $43,452.00
05/01/2024 566000 LABYRINTH SMART MOBILITY INC $43,452.00
06/01/2024 566000 LABYRINTH SMART MOBILITY INC $43,452.00
06/01/2024 566000 LABYRINTH SMART MOBILITY INC $43,452.00
08/01/2024 566000 LABYRINTH SMART MOBILITY INC $43,452.00

Definitions

  • Appropriated Funds: Total amount of authorized funding set aside for a specific purpose
  • Programmed Funds: Estimate and Apportionment (E&A) approved contracts, personnel services, Board Bill approved Intergovernmental agreements (IGA)
  • Expenditures: Total amount spent by departments

Notes and Contact

ARPA(SLFRF and ERA) reporting will be updated on a rolling monthly basis.

The Project and Expenditure data reported is through Aug 30, 2024.

The data was last updated on Oct 15, 2024.

ARPA - American Rescue Plan Act ($510,518,052.20)
SLFRF - Coronavirus State and Local Fiscal Recovery Funds ($498,076,054.00)
ERA - Emergency Rental Assistance ($12,441,998.20)

Please contact STLARPA@stlouis-mo.gov if you have questions about the data.

See Also

An overview of ARPA data can also be found on the ARPA Transparency Portal

Was this page helpful?      



Comments are helpful!
500 character limit

Feedback is anonymous.