Railroad Crossings Quiet Zone Compliance

The City of St. Louis is making upgrades at railroad crossings to comply with Federal Railroad Administration regulations related to train horns.

Nov. 6, 2026: 

Railroad Quiet Zone Status Returning to the City of St. Louis
Residents living near railroad crossings can expect train horns to cease in 7 to 10 days.

Today, the City of St. Louis received notice from the Federal Railroad Administration (FRA) that the City has successfully met the requirements established by the FRA to retain its quiet zone compliance. This means that train engineers will no longer be required to sound their horns at crossings throughout the City.

According to the FRA, railroads have been notified of the quiet zone compliance. While the reinstatement of the quiet zones goes into effect immediately, it will take several days for all systems and protocols to be updated and train horns to cease.

All railroad crossings inspections by the FRA were completed last week. Our crews received positive feedback from the inspectors and all crossings passed inspection.

The Traffic and Lighting Division completed all necessary documentation, including traffic counts, and submitted the information to the FRA on Monday, Nov. 2.

The reinstatement of railroad quiet zones follows an organized and focused approach by the mayoral staff and the Street Department’s Traffic and Lighting Division.

Original projections indicated that quiet zones would be reinstated by mid to late December, but the City completed the needed upgrades, passed inspections, and submitted final documentation to the FRA well ahead of schedule. 

General Overview

As of Sept. 10, the Federal Railroad Administration (FRA) formally suspended all quiet zones within the City of St. Louis. Railroads operating through the City have been directed to resume routine train horn sounding at all affected crossings.

The Office of Mayor Cara Spencer was made aware of the FRA’s actions to suspend the City’s quiet zones via email late on Sept. 10, 2026. Unfortunately, the FRA had been sending communications by email to a former director of operations who has not worked for the City for 16 months.

Once learning of the FRA’s requirements, the mayoral staff and City department leaders held an emergency meeting on Friday, Sept. 11, and submitted a request to the FRA for an extension before the quiet zone was suspended. That request for extension was denied.

The Street Department Director was appointed the city lead and immediately began verifying the FRA crossing list, establishing evaluation and repair teams, and built a plan of action based on the FRA’s information.

With initial planning complete, the Traffic and Lighting Division within the Street Department began the work at railroad crossings on Wednesday, Sept. 16, removing out-of-date railroad bars, inserting “stop bars” (painted bars in front of the crossings), and expedited an order for hundreds of new signs, all to bring the crossings into compliance as quickly as possible.

Railroad Crossings Map

Railroad Crossings At Grade

View larger map

What Is Required

The FRA’s initial inspection indicated the City of St. Louis needed to implement upgrades at 88 railroad crossings. Since then, the FRA provided a list of 187 railroad crossings to be upgraded.

  • Railroad crossing signs at each location must be changed from a 30-inch sign to a 36-inch sign. COMPLETED ON OCT. 19
  • Former stop bar road markings must be removed. COMPLETED ON OCT. 5
  • New stop bar road markings must be painted. COMPLETED ON OCT. 7
  • The city completes required documentation for each crossing located in a corridor. COMPLETED ON NOV. 2
  • The FRA inspects all crossings in a corridor once repaired and related repair documentation received. COMPLETED ON OCT. 30

Timeline

The City focused repairs first on corridors with high residential density and occupancy. We asked the FRA to reinstate quiet zone status in areas that have completed upgrades and inspections with the understanding that the traffic counts and final documentation will soon follow.

Unfortunately, the FRA has denied that request and advised the quiet zones will only be reinstated when all the inspections are completed and all paperwork is turned in. We remain in contact with our federal delegation about this important matter.

Progress Updates

Week of Nov. 2:

Quiet Zone Compliance Reinstated: Following the successful completion of inspections at all railroad crossings last week, our Traffic and Lighting Division submitted final documentation, including traffic counts, ahead of schedule on Mon., Nov. 2. The FRA expedited their documentation review process and sent notification on Friday, Nov. 6 that the City has successfully met the requirements to retain its quiet zone compliance.

Week of Oct. 26:

Inspections nearing completion: Inspections have continued this week and will be completed by end of day Friday, Oct. 30. All crossings are successfully passing inspection.

Paperwork and traffic counts in process: Each railroad crossing has corresponding paperwork and traffic counts to be completed. As the inspections are finalized, this documentation can also be finalized and will be submitted by the end of next week, Friday, Nov. 6.

Week of Oct. 19:

Upgrades completed: Physical upgrades have been completed at all railroad crossings requiring upgrades.

Inspections have begun: FRA inspectors began reviewing physical upgrades onsite and inspections are going smoothly. Of the 35 crossings inspected as of end of day Thursday, Oct. 22, all have been found to be in compliance.

County crossings to be taken off list: FRA has agreed to remove most of the county crossings that had been included on the City of St. Louis list. A few crossings at the city/county border will remain on our list due to the impact on city residents.

Week of Oct. 12:

Signage installation: In less than one week since new 36-inch signs were delivered to City warehouses, signs have been installed at 90 percent of the railroad crossings requiring upgrades.

Documentation: As part of the documentation process, traffic counts are needed at each railroad crossing requiring upgrades. Those traffic counts are currently being conducted.

Week of Oct. 5: 

Pavement Markings to be Completed: Grinding of former road markings was completed on Monday, Oct. 5, and painting of new stop bar road markings across city crossings will be completed on Wednesday, Oct. 7.

Signage Delivery Pending: Expedited delivery of required 36-inch advance warning signs is expected next week. Street Department crews are scheduled to begin installation immediately upon arrival.

Corridor-by-Corridor Reinstatement Approved: The FRA has officially agreed to reinstate quiet zones incrementally on a corridor-by-corridor basis as physical repairs and documentation are completed, rather than waiting for all 187 city crossings. Work is being prioritized in areas with high residential density.

Week of Sept. 28:

Crews have completed grinding out former stop bar road markings at 120 crossings and have painted new stop bar road markings at 20 crossings. Grinding should be completed next week, then crews will fully transition to painting new stop bars. Signs are expected to be delivered late next week. Installation of signs will begin as soon as we receive them.

Week of Sept. 21: 

All signs have been ordered. Crews are removing former stop bar road markings.

Week of Sept. 14: 

Removed out-of-date railroad bars, inserted “stop bars,” and expedited an order for hundreds of new signs.

Upgrades to Railroad Crossings Videos

Contact

Department of Streets

stlstreetdept@stlouis-mo.gov

(314) 647-3111

1900 Hampton Ave
St. Louis, MO 63139

Monday thru Friday, 8:00 - 4:30

Contact the Department of Streets

Did you notice an error? Is there information that you expected to find on this page, but didn't? Let us know below, and we'll work on it.

Was this page helpful?



Comments are helpful!
500 character limit

Feedback is anonymous.