Sewer Lateral Lines Account in FY 2024
Expenditures under account Sewer Lateral Lines (564502) for the 2024 fiscal year
Totals
Budget
$1,800,000.00
Total budget for FY 2024.
Total Expended
$775,168
43% expended of total programmed funds
Total amount expended in FY 2024.
Downloads
All expenditures made under account Sewer Lateral Lines (564502) for the 2024 fiscal year.
Browse Expenditures
Totals by Cost Center
Cost Center | Title | Budget | Expended | % Expended |
---|---|---|---|---|
510003 | Director of Streets Lateral Sewer Program | $1,800,000 | $775,168 | 43% |
Totals by Supplier
Number | Name | Total Expended |
---|---|---|
100003 | A & A PLUMBING & DRAINLAYING | $2,890.00 |
100026 | AAA CONSTRUCTION | $21,940.00 |
100249 | ALL PURPOSE GENERAL CONTRACTRS | $40,241.76 |
100823 | BCI CONTRACTING | $85,445.56 |
101670 | CEHIC CONTRACTING LLC | $7,685.00 |
102345 | D & V CONSTRUCTION | $7,377.00 |
103042 | ERVIN'S CONSTRUCTION LLC | $172,461.85 |
103049 | ESEHIC CORP | $92,943.00 |
104984 | JOHN MESS PLUMBING AND DRAINLAYING | $36,990.00 |
105456 | KUCHAR TRUCKING & GRADING, INC | $22,031.00 |
105905 | LULIC, LLC | $97,310.00 |
106108 | MASTER RENOVATIONS CO. | $79,665.85 |
107042 | NIKSICO CONSTRUCTION LLC | $26,240.00 |
107350 | PARKER ADAMS LLC | $3,877.00 |
108386 | S AND B CONTRACTING LLC | $78,070.00 |
Totals by Fund
Fund | Title | Budget | Expended | % Expended |
---|---|---|---|---|
1117 | Sewer Lateral Repair Program | $1,800,000 | $775,168 | 43% |