Arterial Street Paving - Enright to Florissant 2022A
Design and construction of various infrastructure improvements which may include paving, striping, curb ramps, traffic calming, and other infrastructure features on sections of roadway within the identified project limits from Enright to Florissant
Project Appropriation
Project Appropriation
$526,500.00
Total Programmed Funds
Total Programmed Funds
$526,500.00
100.0% programmed of total appropriation
Total Expenditures
Total Expenditures
$526,500.00
100.0% expended of total appropriation
- Category: [6.1] Provision of Government Services
- Project Number: 100796
- Ordinance: 71494
Project Expenditures
Project Expenditures
Date | Account | Vendor | Amount |
---|---|---|---|
02/02/2023 | 566006 | ST. LOUIS AMERICAN NEWSPAPER | $258.00 |
02/02/2023 | 566006 | ST. LOUIS AMERICAN NEWSPAPER | $258.00 |
01/23/2024 | 566000 | CBB TRANSPORTATION ENGINEERS | $23,611.11 |
09/23/2024 | 564500 | SBC CONTRACTING, INC. | $144,002.47 |
10/04/2024 | 566000 | CBB TRANSPORTATION ENGINEERS | $21,632.00 |
11/06/2024 | 564500 | SBC CONTRACTING, INC. | $336,738.42 |
Definitions
- Appropriated Funds: Total amount of authorized funding set aside for a specific purpose
- Programmed Funds: Estimate and Apportionment (E&A) approved contracts, personnel services, Board Bill approved Intergovernmental agreements (IGA)
- Expenditures: Total amount spent by departments
Notes and Contact
SLFRF reporting will be updated on a rolling monthly basis.
The Project and Expenditure data reported is through Jan 31, 2025.
The data was last updated on Mar 11, 2025.
SLFRF - Coronavirus State and Local Fiscal Recovery Funds ($498,076,054.00)
Please contact STLARPA@stlouis-mo.gov if you have questions about the data.
See Also
An overview of ARPA data can also be found on the ARPA Transparency Portal
Feedback is anonymous.