Municipal Garage Repairs 2022

This work included the design and construction of concrete and masonry repairs to the City of St. Louis Municipal Garage to repair failed concrete and protect it from future salt infiltration and deterioration.

Project Appropriation

Project Appropriation
$595,648.90

Total Programmed Funds

Total Programmed Funds
$595,648.90
100.0% programmed of total appropriation

Total Expenditures

Total Expenditures
$595,648.90
100.0% expended of total appropriation

Project Expenditures

Project Expenditures
Date Account Vendor Amount
02/28/2023 564500 CONCRETE STRATEGIES LLC $105,081.87
03/02/2023 566000 TORRISI PLUMBING SERVICES INC. $62,318.00
03/31/2023 564500 CONCRETE STRATEGIES LLC $180,321.88
04/30/2023 564500 CONCRETE STRATEGIES LLC $76,866.87
05/31/2023 564500 CONCRETE STRATEGIES LLC $65,084.50
06/21/2023 564500 CONCRETE STRATEGIES LLC $65,647.38
11/29/2023 564500 CONCRETE STRATEGIES LLC $40,328.40

Definitions

  • Appropriated Funds: Total amount of authorized funding set aside for a specific purpose
  • Programmed Funds: Estimate and Apportionment (E&A) approved contracts, personnel services, Board Bill approved Intergovernmental agreements (IGA)
  • Expenditures: Total amount spent by departments

Notes and Contact

SLFRF reporting will be updated on a rolling monthly basis.

The Project and Expenditure data reported is through Jan 31, 2025.

The data was last updated on Mar 11, 2025.

SLFRF - Coronavirus State and Local Fiscal Recovery Funds ($498,076,054.00)

Please contact STLARPA@stlouis-mo.gov if you have questions about the data.