Revenue Replacement Funds: SLDC Building Stabilization Manager

The role of the Building Stabilization Manager is to provide project management and coordination among departments and stakeholders as it relates to the private vacant building stabilization program known as Stable Communities STL (SCSTL). These departments and stakeholders that the Building Stabilization Manager works with include the Building Division, Mayors Office, Problem Properties, PDA, commercial contractors, community stakeholders and the SCSTL Committee. The daily tasks of the Building Stabilization Managers include, but are not limited to, assistance with development of scope of work; verification of structural condemnation; property selection, property owner notification; contract bidding; and tasks related to construction. Due to the complex and sensitive nature of the SCSTL program and the fact that all other administrators of the program have multi-faceted job responsibilities, it is important that the Building Stabilization Manager has a job role that is solely focused on the development and administration of this program.

Project Appropriation

Project Appropriation
$400,000.00

Total Programmed Funds

Total Programmed Funds
$400,000.00
100.0% programmed of total appropriation

Total Expenditures

Total Expenditures
$41,957.58
10.5% expended of total appropriation

Project Expenditures

Project Expenditures
Date Account Vendor Amount
04/11/2024 566067 ST. LOUIS DEVELOPMENT CORP. $41,957.58

Definitions

  • Appropriated Funds: Total amount of authorized funding set aside for a specific purpose
  • Programmed Funds: Estimate and Apportionment (E&A) approved contracts, personnel services, Board Bill approved Intergovernmental agreements (IGA)
  • Expenditures: Total amount spent by departments

Notes and Contact

SLFRF reporting will be updated on a rolling monthly basis.

The Project and Expenditure data reported is through Nov 30, 2024.

The data was last updated on Feb 06, 2025.

SLFRF - Coronavirus State and Local Fiscal Recovery Funds ($498,076,054.00)

Please contact STLARPA@stlouis-mo.gov if you have questions about the data.

See Also

An overview of ARPA data can also be found on the ARPA Transparency Portal